How to Make a Gantt Chart in Excel: Step-by-Step Guide with Formulas

A Gantt chart shows at a glance which task runs when, what depends on what, and where a project is stuck. You don’t need expensive software: with one table, three formulas and conditional formatting, Excel draws the plan for you.

by Keywan Fakhri, Industrial Engineer (M.Sc.), Konstanz · Updated: 23 October 2026

What is a Gantt chart?

A Gantt chart is a bar schedule: tasks on the left, a timeline of days or weeks across the top, and each bar shows when a task starts and how long it lasts. It works for anything with a deadline – moving a warehouse, rolling out software or opening a restaurant.

Step 1: Set up the task list

Create a table with these columns. Format it as an Excel table with Ctrl + T so formulas extend automatically.

ColumnContent
A – Taske.g. “Order shelving”
B – OwnerName or team
C – StartDate
D – Duration (days)Number
E – EndFormula
F – Progress0–100 %

Step 2: Calculate the end date

The end date follows from start and duration. To skip weekends, use working days:

End (calendar days) = C2 + D2 − 1

End (working days) = WORKDAY(C2, D2 − 1)

If a task depends on another, set its start to the next working day after that task ends: =WORKDAY(E2, 1). When the first task moves, the whole plan moves with it.

Step 3: Build the timeline

From column H, enter the project start date in row 1 and next to it =H1 + 1 for days or =H1 + 7 for weeks. Drag the formula to the right. With the number format DD/MM and narrow columns (width 3–4) you get a compact timeline.

Step 4: Draw bars with conditional formatting

Select the area below the timeline (e.g. H2:AF30) and choose Home › Conditional Formatting › New Rule › Use a formula. This rule colours every cell whose date falls between start and end:

=AND(H$1 >= $C2, H$1 <= $E2)

The dollar signs matter: H$1 locks the timeline row, $C2 and $E2 lock the start and end columns.

Step 5: Show progress and delays

Two more rules turn the plan into a status report. The first colours the completed part darker:

=AND(H$1 >= $C2, H$1 < $C2 + $D2 * $F2)

The second marks open days that are already in the past – the delay – in orange:

=AND(H$1 >= $C2 + $D2 * $F2, H$1 <= $E2, H$1 < TODAY())

A fourth rule, =H$1 = TODAY() with a red border, marks today. Mind the rule order: delay and progress go above the base rule.

Common mistakes

  1. Text instead of dates: if a date is left-aligned, Excel doesn’t see it as a date and the formulas return nothing.
  2. Missing dollar signs: without $ the references shift when copied and the bars jump.
  3. Timeline too fine: for projects longer than three months, weeks read better than days.
  4. Dependencies typed by hand: link start dates with formulas, or the plan breaks after the first change.
  5. No progress tracked: a Gantt chart without actual status is just a wish list.

When Excel is enough – and when it isn’t

Excel works well for projects with up to about 50–80 tasks and a small team. If you need resource planning across many projects, an automatically recalculated critical path or many people editing at once, a project management tool is worth it.

Free Excel template

The Project Gantt Manager has every step of this article built in: the Gantt chart draws itself, late tasks turn orange, and a dashboard compares progress and budget against the plan. No macros, 12 languages.

Frequently asked questions

Does Excel have a built-in Gantt chart?

Excel has no dedicated “Gantt” chart type. You can rework a stacked bar chart or – more flexibly – draw the bars directly in cells with conditional formatting, as in this guide.

Does this work in Google Sheets?

Yes. The formulas and conditional formatting work the same way there.

How many tasks can an Excel Gantt chart handle?

Technically a lot. It stays readable up to about 50–80 tasks. Group larger projects by phase.